学术论文

      铁水供应对转炉群布置的影响

      Hot Metal Supply Impactd on Converter Layout

      摘要:
      在实测和解析某钢厂2座和3座转炉并排布置时的铁水包作业过程时间的基础上,提出了3座和2座转炉并排布置时,铁水供应的限制性环节;说明3座转炉并排布置不适应快速转炉的生产要求.计算在不同限制环节下,单座转炉的最大年生产能力.同时计算了日本新型转炉群布置的年生产能力,探讨了其对高速连铸的适应性.
      Abstract:
      The process time of hot metal ladle was measured and analyzed, and the neck of hot metal supply was pointed out when two or three converters are located in one line. The most annual capacity of one converter was calculated in different neck. The result is that three converters located in one line are not suitable for the production demand of fast converter. In the meantime, annual capacity is calculated, and the adaptability is discussed to the higher speed continuous casting about new converters layout in Japan. The references are provided for enterprise alteration in our country.
      作者: 刘茂林 [1] 徐安军 [1] 吴晓东 [1] 田乃媛 [1] 陆志新 [2] 孙国伟 [2]
      Author: LIU Maoling [1] XU Anjun [1] WU Xiaodong [1] TIAN Naiyuan [1] LU Zhixin [2] SUN Guowei [2]
      作者单位: 北京科技大学冶金学院, 宝山钢铁集团公司生产部,
      刊 名: 北京科技大学学报 ISTICEIPKU
      年,卷(期): 2001, 23(2)
      分类号: TF748+.02
      机标分类号: TF5 TF3
      在线出版日期: 2004年1月8日